by drbadmin | Nov 23, 2022
Willis Towers Watson Henley-on-Thames About this Project Project value: £60kDuration: 3 weeks Dilapidation Works. Working for a valued return client we stripped out all the existing partitions, power, and various fixtures and fittings (Back to CAT A), thoroughly deep...
by drbadmin | Nov 23, 2022
Leacon Road About this Project Project value: £360kDuration: 14 weeks Competitive tender, shortened programme duration by 6 weeks. Installation of a new 1st floor mezzanine area for offices and rooms, serviced by a new fire escape, creation of 2 blockwork rooms for...
by drbadmin | Nov 23, 2022
Korn Ferry About this Project Project value: £500kDuration: 20 weeks RTO Project – Return to Office CAT B Works were carried out in 4 phases over 4 floors consisting of new floor finishes, bespoke joinery, AV installation, lighting, power and FA modifications,...
by drbadmin | Nov 23, 2022
Starr Insurance About this Project Project value: £350kDuration: 6 weeks Stepped in at extremely short notice after a client had been let down by another contractor, 1 week lead in with just over 6 weeks onsite. Works consisted of striping out partitions, reducing...