Starr Insurance
About this Project
Project value: £350k
Duration: 6 weeks
Stepped in at extremely short notice after a client had been let down by another contractor, 1 week lead in with just over 6 weeks onsite.
Works consisted of stripping out partitions, reducing floor levels to take new timber flooring, creating new office and meeting spaces, mechanical and electrical adaptions to suit the new spaces, new wall and floor finishes, installation of bespoke reception to include desk and meeting booths.